Maid of the Mist Mayday
It is not always the size, weight or volume of lifts that poses the greatest challenge for a project. Sometimes the feat is just navigating a previously uncharted territory and accomplishing the difficult task in a tight time frame. The payoff is the satisfaction of knowing that the crew overcame the challenges, built something that benefits the community and improves an old abandoned land area. Clark Rigging and Rental Corp. of Lockport, New York, and two of its cranes, the Terex® AC 350/6 and Terex AC 500-2 all terrain cranes, recently completed one of these jobs. The crane rental contractor was one of the first responders to help the State of New York rescue a family-run business that has thrilled countless visitors and many celebrities with the majesty of the Niagara Falls. For more than 150 years, the Maid of the Mist ships have operated on the Niagara River Gorge. Initially, they served as ferries to transport people, cargo and carriages across the Niagara River below the waterfalls. In the modern era, the Maid of the Mist Corporation had leases in both Canada and New York to take spectators on a memorable tour of Niagara Falls. “The vessels would dock for the winter in Canada, since they had the infrastructure,” says Steve Clark, vice president of Clark Rigging and Rental Corp. That is, until the Maid of the Mist Corporation lost both its lease to operate in Canada and the docks that went along with it. With no place to dry-dock the vessels during the winter on the New York side of the Falls, the Maid of the Mist Corporation faced the potential of ceasing operations and the State of New York was in jeopardy of losing tourism revenues. Both the Corporation and New York representatives quickly searched for a suitable location to build a dry dock facility. With few viable options, the State came up with a solution that would allow it to transform an abandoned property, while enabling the Maid of the Mist voyages to continue. “They chose the site of the old Schoellkopf Power Station for the new dock,” mentions Mr. Clark. “The plant collapsed into the Niagara River Gorge in the 1950s.” The site north of Niagara Falls had the full backing of the State for the $32 million renovation project. “We value the Maid of the Mist; we wanted to keep the Maid of the Mist here; we had a parcel we believed we could be better utilizing for the State and for tourism; and we put the two together,” said New York Governor Andrew M. Cuomo while visiting Niagara Falls on December 4, 2012. 50 Years Untouched “There was no access to the site for the equipment to build the harbor crane. Everything had to be lowered by crane from a cliff overlooking the gorge approximately 45.7 m above the river,” added Melanie Parker, sales administrator for Clark Rigging. Clark Rigging’s crew was first on site with its 350 t capacity class Terex AC 350/6 all terrain crane, equipped with its full counterweight and 64 m main boom. Starting in May of 2013 and lasting for six weeks, the AC 350/6 crane was the workhorse of the project, aiding with initial site clean-up efforts. “We averaged 75 picks a day with the crane, lowering equipment down into the gorge,” says Mr. Clark. While Clark Rigging’s AC 350/6 crane was lowering supplies to clear the gorge of trash and overgrowth and prepare the riverside for a new dry dock and observation area, work commenced on constructing a buck hoist elevator for a more efficient way to get workers down to the project site. Additionally, a high capacity ringer crane was erected to lower cranes, trailers, pieces of the harbor crane and other heavy components into the project site. Among the equipment the AC 350/6 all terrain crane lowered into the gorge were skid steer loaders, dozers, all terrain trucks and a 11 t excavator. “We were working at about a 33.5 m radius to lower material 45.7 m into the gorge,” says Steve Clark. “It’s a challenge working from that height in off-road conditions, where the terrain is not level.” Lifting the Mist Since there were no access roads leading to the dock area, the AC 500-2 crane was placed into the gorge from atop the cliff by the ringer crane. “It was lowered in two pieces, the main crane and the boom,” says Steve Clark. “The counterweight was lowered two at a time.” A Terex RT 655 rough terrain crane was also placed into the gorge. “The rough terrain crane assisted with boom installation on the AC 500-2,” says Melanie Parker. Since the ringer crane did not have the reach to extend to the river’s edge, a trailer was also positioned in the gorge to efficiently transport the harbor crane components to the edge of the water. For harbor crane construction, a total of eight components with an average weight of 63.5 t were hoisted and positioned by the AC 500-2 crane. Additional components positioned by the Terex all terrain crane included the 54.4 t crane base, 63.5 t slewing gear and two 63.5 t floating docks. A 81.6 t capacity, 17.7 m spreader beam was placed in a tandem lift using the AC 500-2 crane and a crawler crane. “We worked at a short 9.1 m radius with the AC 500-2 crane,” says Mr. Clark. “There were no major challenges with the lifts, and we were finished with the harbor crane within two weeks.” On November 1, 2013, the two Maid of the Mist vessels were pulled from the Niagara River by the 181.4 t harbor crane and placed on their newly built dry dock at the former Shoellkopf Power Station site. The site’s two new platforms – one atop of the gorge and a second alongside the Niagara River – are now connected by a new elevator, giving pedestrian accessibility to the Niagara River Gorge, so the visitors will have a new way to experience the grandeur of this national treasure.
|
© InfraStructures - Tous droits réservés - All rights reserved |