Mixing and Dispersing Technology Specialist ystral Opens New Trial Centre

 

 

 

The machine and systems manufacturer ystral has opened a new trial centre at its headquarters in Ballrechten-Dottingen, Germany. The new facility enables the company to carry out more customer trials than before while processing a broader range of raw materials.

The ystral group is an owner-managed family business with almost 300 employees in total. ystral designs, engineers and manufactures highly efficient mixing, dispersing and powder induction machines, as well as process systems, used worldwide in the chemical, paints and coatings, food, pharmaceutical, household and cosmetics industries, as well as in battery production. At the ystral trial centre, companies from these sectors can develop new products and processes or optimise existing ones, train their operating personnel on ystral machines, and test the mixing technology provider’s solutions.

ystral has already conducted a number of tests in the new trial building. Its major importance to the company’s commercial success became evident from the outset: following trials, a printing ink manufacturer awarded ystral an order with a project volume worth several million euros.

“Our experience shows that tests carried out in our trial centre almost always lead to collaboration,” said Uwe Klaumünzner, head of Development and Trials at ystral.

Trials with flammable and explosive media
The new trial area complies with statutory explosion protection and water protection requirements, and the machines used are ATEX-compliant. Trials with flammable and explosive media are possible there following case-by-case assessment. During the tests, users do not need to be on site themselves, but can also follow proceedings remotely via livestream.

Comprehensive analysis options
In the company’s in-house laboratory, samples can be examined under an optical microscope with respect to various parameters. This includes both density measurement and particle size analysis by means of dynamic light scattering. In addition, viscosities can be determined using various measurement methods, with and without tempering, and curves for different shear rates can be recorded.

With a construction and commissioning phase of just under 12 months, work on the trial centre progressed exactly according to plan. The new trial building was constructed in a compact cubic design on an area of around 150 m2 and can, in future, be expanded with an additional trial building on an adjacent open site.

“At our current company size, we are very well positioned with our existing trial facilities,” said Peter Manke ystral managing director and co-owner. “However, we planned our new trial centre from the outset in such a way that expansion is possible.”

Source: ystral GmbH maschinenbau + processtechnik

Partagez sur Facebook / Share on Facebook   Partagez sur LinkedIn / Share on LinkedIn