Refinery Maintenance Benefits from FOCUS30’s Space and Time-Saving Strengths
Over time, this makes maintenance more complex. With a facility full of live and tightly packed critical equipment, safety becomes the key priority; closely followed by efficiency. When a refinery undergoes maintenance activity, some operations at the site must halt whilst essential work is carried out. Therefore, any unnecessary downtime can add significant cost to a project. As part of maintenance activity at ExxonMobil’s Fawley Refinery in the UK, Mammoet recently supported with the exchange of a reactor head in the FCC (Fluid Catalytic Cracker) unit. Mammoet utilized its self-erecting FOCUS30 pedestal crane, which performed the operation with ease – replacing the old 356 t reactor head in less time than other cranes while taking up a footprint slightly larger than a 5-a-side football pitch. Focusing on the challenge to perform heavy lifting in a constrained space Despite this, its boom had to be carefully assembled over live pipework as there wasn’t enough free space to construct it at ground level. Eighteen years on, with even less site space to carry out this project, Mammoet’s engineers suggested using the FOCUS30. Dubbed ‘the crane that builds itself’, it has been specifically designed to perform heavy lifting in facilities with complex infrastructure and limited space.
This high-capacity pedestal crane has a boom that is erected vertically in sections, instead of horizontally. Each boom section is inserted like a jacking cartridge before being lifted to make room for the next underneath. This not only allows for faster assembly, but for the crane to be built in a footprint measuring just 34 by 42 m. It also means that the crane’s boom does not need to be laid flat before erection, potentially blocking access roads on site. At the planning stage, Mammoet’s engineers conducted a full 3D scan of the refinery’s reactor and, using in-house planning software Move3D, created a visualization of the project to show how the pedestal crane would be positioned and utilized on site. By utilizing this software in combination with 3D scan data, it was possible to identify any clashes in the highly congested site. The lift’s close proximity to an absorption column demanded a level of scrutiny and accuracy that couldn’t be provided by a traditional 2D approach. By carefully positioning the FOCUS30 crane around existing infrastructure, hardly any alterations were needed in the field. Only one large pipe was identified early in the engineering process, and this was able to be removed without delay. The FOCUS30 was configured with a divisible superlift tray of 900 t and 400 t sections, which made movement of the ballast fast and simple, while making sure that the crane did not need to slew over live pipe racks with the load. The FOCUS30 is also much less susceptible to high winds than alternative crawler cranes, which would typically have to boom down at around 16 m/s wind speeds, causing significant disruption on site. By storm anchoring itself to its own outriggers, the FOCUS30 can withstand conditions more than twice as harsh, giving owners peace of mind projects will not suffer significant wind delays. Pedestal crane built for faster, safer refinery operations Its use alongside Move3D allows maintenance projects at sites that have existed for many decades, changing year-by-year, to proceed with confidence that every millimeter has been accounted for. The FOCUS30 has 30,000 tm of load moment, yet has only one-sixth of the footprint, compared to currently commercially available crawler cranes with comparable strength. It solves three of the biggest challenges that plant owners face: lifting capacity, space, and time. “It takes around three to four weeks to assemble the FOCUS30. By comparison, a heavy lift crawler crane would have taken around 5 weeks,” explained – as Koen Totté, Sales manager at Mammoet. “We would also have needed to build its boom over the pipe rack, which would have been very time consuming and added risk due to working at a height of around 10 mover this live plant. With the FOCUS30 we could work from inside the crane’s footprint, and not have to work at great height, making it a much quicker and safer alternative.”
|
© InfraStructures - Tous droits réservés - All rights reserved |