Advertisement |
Advertisement PDAC - The World's Premier Mineral Exploration & Mining Convention |
Record-Breaking Dragline Relocation Achieved Using SPMTs in Australia
BHP Mitsubishi Alliance (BMA) entrusted Mammoet with the relocation of a 3,100 t Marion 8050 dragline from one end of the Peak Downs coal mine in Queensland, Australia, to another – a full 27 km away. With a deadline to achieve the relocation, it was sub-optimal to allow the dragline to travel under its own steam. The solution? Jack up the dragline so it could be carried by Mammoet Self-Propelled Modular Transporters (SPMTs). SPMTs can travel up to 5 km/h. In comparison, a dragline can cover approximately 1 km in 12 hours.
What’s more, with extra equipment needed to complete the job and all imports subject to strict customs requirements, Mammoet would need to call on its global expertise and fleet to ensure smooth execution. Eight JS500 towers were set up underneath the dragline for the jacking operation. Once it was elevated to 2.5 m, a configuration of 5x28 lines of SPMT were positioned underneath the load to transport it. For the jacking stage, it was vital the engineers understood the weight and center of gravity of the machine. Due to the dragline’s age, information about it was limited, so they worked from a starting point of what was available for machines of a similar age. While there were some nuances, the dragline was safely and efficiently lifted. Its weight was evenly distributed across 560 tires, resulting in a ground bearing pressure of less than 9 t/m2. “In the past, dragline jacking in Australia has been performed using climbing jacks, which require manual handling of timber stacks to gradually lift the load,” explained Jack Whittaker, project manager at Mammoet. “The JS500 system requires fewer jacking towers and uses cassettes, which are inserted at its base. This saved a lot of time, resulted in less equipment and removed the need for manual handling.” Due to the distance and intense Queensland heat, a canopied seat was installed on the deck of the front SPMT. This meant the control box could be mounted instead of carried, and the driver could be shielded from the sun. The team had a 72-h window for the railway line closure. In that time they had to construct the temporary ramp over the track, make the crossing safely and return everything back to its original state. “One of the key reasons that BMA reached out to us was because the Aurizon rail crossing is a critical line – transporting coal from different mines in the region to the coast for exporting,” added Laura Ewen, branch manager at Mammoet. “Peak Downs had competing projects in the area at the time, and the shutdown crossing window wouldn’t align again for another three months. The Dragline was required for coal extraction in the southern pits for production. A record-breaking dragline relocation The other benefit of this method was logistical – the ancillary equipment required to move a dragline, along with a portable substation connected via a long “umbilical” cable linked directly to overhead power cables on site, was not needed because everything was powered by the SPMTs. Typically requiring over a month to transport, Mammoet has now set a new benchmark for dragline transportation by relocating this unit 27 km to Peak Downs Mine in just 10 days, achieving 8 km/d and significantly minimizing downtime for the Marion 8050.
|
© InfraStructures - Tous droits réservés - All rights reserved |