PERI Assists with the Construction of the New Headquarters of HeidelbergCement

 

 

 

The new group headquarters of the building materials manufacturer HeidelbergCement, in Heidelberg, Germany, is stunning with its bright, light-flooded rooms and the radial elements made of white concrete. Within a 16-month construction period, almost 97,500 m2 of formwork solutions were used – including customized PERI special formwork elements.

The building clearly demonstrates what is possible with concrete – and do so in the most impressive way possible.

The results of using SB 4 architectural concrete and the finest white concrete are visible in the many architectural highlights. Spectacularly twisted tree-like supports, creatively patterned facade prefabricated concrete elements and sharp-edged beams in a radial pattern, are particularly eye-catching. A total of 31,500 m3 of concrete was used for the construction of the building, which consists of 3 interconnected parts of different heights.

The architectural firm AS+P Albert Speer + Partner was responsible for the project as general planner and carried out the design in cooperation with W+ Architektur- und Ingenieurgesellschaft mbH, with the latter providing the consulting office for the client’s project manager. The complex construction work was carried out by the building contractor Diringer & Scheidel.

PERI and HeidelbergCement combined their architectural concrete expertise for the execution of this project. In doing so, existing limits were extended, and the wide range of possibilities offered by concrete and the PERI products were exploited.

The bright, curved facade of the new headquarters impresses with its delicate filigree – despite the use of the solid building material concrete. The 11.75 m-high facade supports are particularly striking. In order to construct the facade columns and their particularly smooth concrete surfaces in the highest quality, PERI timber girder formwork with multi-layer panels coated with melamine resin was used.

The focal point of the approximately 11 m-high foyer of the HeidelbergCement headquarters is formed by 2 groups of tree-like supports, which from a structural point of view, serve as the root of the building. Each consist of 3 square cross-sections inclined towards each other, crossing approximately in the lower third. In compliance with the architectural concrete quality required, only one panel joint is visible over the entire column height and no fastening screws, clamping holes and formlining joints are visible.

Due to the very high architectural concrete requirements, the required fresh concrete static pressure of 200 kN/m2 and the tough space limitations in the foyer, special formwork made of wood was not an option for implementing the tree-like supports. PERI therefore developed a highly complex 3D special formwork made of steel elements with an overall height of 150 mm. The basis for which was carried out completely via the CAD systems PERI CAD and RHINO.

The supporting structure of the prepared special column formwork was a sophisticated honeycomb structure consisting of 63 CNC laser-cut individual parts. They were assembled as a plug-in system to avoid time-consuming welding. Each individual component had to be newly constructed and statically-dimensioned. A total of around 12.7 t of steel was used to produce this formwork. The 5 mm-thick steel formlining was then attached to the supporting structure to withstand the high level of fresh concrete pressure. At the point where the arms of the 3 tree-like supports cross, additional external ring constructions were attached to specifically counteract deformation of the steel.

In addition to the requirements for the color and structure of the architectural concrete surface, another special feature was the pouring of the concrete. Unlike in most other cases, the concrete was not poured from above but from below. A concrete distribution system transported a total of 30 m3 of concrete simultaneously into 3 column sections and pressed the concrete upwards up to 11 m via 3 pump hoses in the formwork.

Additional sensors of the PERI InSite Construction (ISC) Pressure Monitoring Set integrated into the formwork made it possible to measure the fresh concrete pressure in real time during the concreting process and to monitor it via the ISC Web Application on the mobile phone. The determined characteristic data for the formwork pressure provided a precise picture of the concreting process of the tree supports.

The walls of the foyer also stand out due to their architectural design. The so-called feature wall is characterized by its recessed, radial pattern, which consists of several prefabricated concrete elements that were retrofitted to the in-situ concrete wall. No visible fastening points or tension holes negatively impact the appearance and there are no visible vertical joints and a only 2 visible horizontal joints at the height of the galleries. The butt joints were concealed by an overcut. In order to be able to realize the 8 cm-thick prefabricated concrete elements (4 cm in the recesses), special formwork was used.

Another challenge was encountered with the dome ceiling, which consists of an uneven cross vault with a circumferential edge upstand in SB 4 grey concrete. This was expected to be formed at a height of up to 7 m and a slab thickness of 25 cm. The formwork solution that PERI developed consisted of a total of 82 3D-designed architectural concrete timber formers. They were mounted onto components of the PERI UP scaffold construction kit and finally sealed. The PERI UP Weather Protection Roof ensured that work could be carried out regardless of the weather conditions.

The casino on the ground floor of the new headquarters offers HeidelbergCement employees ample seating and a commercial kitchen. As one of the project highlights, this room features a special reinforced concrete ceiling with radial sharp-edged beams. These stand out in SB 4 white concrete from the underlying ceiling in SB 2 grey concrete mainly due to the striking shapes and colors. Again, no visible fixing points of the formlining or bracing points of the beam formwork are visible.

For the slab, PERI special formwork developed especially for the project was used, which was later implemented with a total of 64 different diamond-shaped elements preassembled in the factory. The special feature of the casino: first, the beams were created by simultaneously forming them from the outside to the inside with 2 pumps. Only then, after the beams had hardened, was the ceiling concreted.

A total of around 3,000 m2 of project-specific architectural concrete girder wall formwork was used during the project, most of which was preassembled in the factory and delivered to Heidelberg on schedule. The special challenges for the PERI engineers therefore included the intensive planning, the creation of individual special formwork solutions, as well as the support of the site personnel during the implementation of the complex geometries and shapes, and also the punctual provision of materials and coordination of the delivery dates.

Source: PERI Germany

Partagez sur Facebook / Share on Facebook    


© InfraStructures - Tous droits réservés - All rights reserved