Full Power for Power Plant Construction

 

 

 

This year, the catchcry in Töging will be “Water on!” and the Inn canal, partially drained for the last phase of work, will be flooded again. From the dam between Jettenbach and Aschau am Inn, the diverted Alpine river will flow 20 km to the run-of-river power plant Töging, where it will rush a good 31 m into the deep – 410 m3/s, which will be converted into electricity in the powerhouse by 3 machine sets, each consisting of a Kaplan turbine and a generator. Enough to supply 200,000 households in the region.

A thundering spectacle, even though grass will have covered it soon. Nothing will be visible in the lush greenery except for 2 elegant concrete apertures marking the inflow and outflow of the new power plant. The future of hydroelectricity in Töging am Inn in Upper Bavaria will be subterranean: 9 years of hydro energy planning and construction swallowed up by the earth. But this construction site – a moulded, moraine-like, sloping piece of land between the bank of the Inn and the historic structure – has a story to tell. Here, where complex geometric planning meets geological caprice, where humans tame the irrepressible forces of nature a few meters above sea level. In the name of the energy revolution it will feed renewable energy into the grid. Not only has the entirety of civil engineering know-how been called upon here to keep the groundwater in check, methods first had to be sought to pave the way for this bold construction dream – keyword: formwork planning.

3D formwork planning is one of Doka’s key disciplines, demonstrating that also slopes of almost 30° and slab thicknesses of 4 m can be overcome. Doka provides ideal casting moulds for the concrete even when imagination is stretched to its limits. The Doka project technicians have a lot of experience in power plant construction, having realized some fascinating structures: be it modernizing an old power plant building to make it more efficient, building a new one or expanding an existing one; or a mixture of all three, as in the Töging project.

“But here, the geometry of the turbines and inlet slabs was so complicated in several areas that formwork planning wouldn’t have been possible without a comprehensive 3D model,” said senior project technician Stefan Pirkner.

The aim was to understand which negative forms were needed to ensure flawless concreting later on. Over the course of 100 extra project hours, the complex was made comprehensible and the comprehensible was made precise. And the PORR GmbH & Co. KGaA and the construction supervisor Ralph Brenner received the ideal freeform formwork to cope with the demanding geometry.

“We had a contact person from Doka here at all times, and the custom-built modules came to us already preassembled so that we could concentrate on reinforcing and concreting,” said Mr. Brenner.

Even 6-level structures such as stair towers were simple to handle and could be moved easily with a crane. All this gave the construction crew a feeling of security at work – another basis for the very high level of safety at what is currently Germany’s largest hydroelectricity construction site.

Then came the coronavirus. And this was problematic not only for the Doka sales and field engineer. There were scarcely any border crossings or on-site support possible, and almost everything had to be done from home via video calls. However, digital technology such as BIM, 3D planning, real-time concrete monitoring and video conferencing were extremely helpful.

Compared to the historic power plant from the time of the Weimar Republic, built 100 years ago by up to 7,000 workers on what was then Europe’s largest construction site, the new and modern construction architecturally blends modestly into its surroundings – although its performance capability, with 3 vertically anchored turbines, will stand at centre stage.

Bavarian operator VERBUND Innkraftwerke has spent €250 million ($340 million) on their project between Jettenbach and Töging.

The Austrian company Doka is an expert in power plant construction – even when things get complex. Also, due to Austria’s mountainous topography, which makes up three quarters of the land area, 70% of electricity produced in Austria comes from hydropower. That is well above the European average, and even the Kaplan turbine is an invention of the Alpine republic. Historically, Doka is deeply rooted in power plant construction. After all, the name Doka comes from the Austrian DOnauKrAftwerken (Danube Power Plants), for which the first formwork was supplied in the 1950s. Or, in Zehetmayer’s own words: "We have the most experience when it comes to building power plants!"

Source: Doka

Partagez sur Facebook / Share on Facebook    


© InfraStructures - Tous droits réservés - All rights reserved